A shed on bare soil sinks, rots and shifts. A flat concrete pad gives it a base that stays level and stays dry. Here is how to build a concrete pad for a shed.

## 1. Check the shed base size

1. Measure the shed footprint.
2. Add a few inches all round.
3. Check the maker's base requirements.

## 2. Pick the spot

1. Choose ground that drains.
2. Keep the pad clear of the property line.
3. Check the door side faces the way you want.

## 3. Set out the shape

1. Drive stakes at the corners.
2. Check the diagonals match, so the pad is square.
3. Run string lines between the stakes.

## 4. Excavate

1. Strip turf and topsoil to about six inches.
2. Dig out any soft spots.
3. Keep the bottom flat.

## 5. Build the form

1. Set timber boards along the edges.
2. Fix them to stakes so they cannot bow.
3. Check the form is level and square.

## 6. Add and compact the base

1. Fill with crushed stone to about four inches.
2. Compact in two layers.
3. Check the base is level and firm.

## 7. Mix and pour

1. Mix concrete in batches you can place quickly.
2. Pour into one corner and work across.
3. Keep the pour continuous where you can.

## 8. Screed it flat

1. Run a straight board across the form.
2. Work in a sawing motion to level the surface.
3. Fill low spots as you go.

## 9. Finish and cure

1. Float the surface smooth.
2. Cut a slight fall toward the door side.
3. Cover with plastic and keep it damp for a few days.
4. Keep weight off for at least a week.

## 10. Set the shed on top

1. Check the pad is fully cured and clean.
2. Add a damp proof layer under the shed floor.
3. Fix the shed down as the maker instructs.

## Why the base matters more than the slab

Most cracked shed pads fail underneath, not on top. A slab poured over soft fill flexes, and the first crack appears at the corner. Compact the sub base in two thin layers rather than one thick one, and check it with a straight edge before the form goes on. If the ground holds water, add a shallow layer of gravel and a drain to one side so the slab is not sitting in a puddle. A pad that stays dry underneath will outlast three that do not.

## Common mistakes

- Pouring on soft, uncompacted ground.
- A form that bows, giving a curved edge.
- A pad with no fall, so water sits at the door.
- Walking on the slab too soon.
- Skipping the damp proof layer.

## Related guides

- [How to Build a Gravel Parking Pad](/guides/how-to-build-a-gravel-parking-pad/)

- [How to Build a Concrete Curb Along a Driveway Edge](/guides/how-to-build-a-concrete-curb-along-a-driveway-edge/)
- [How to Build a Shed Ramp](/guides/how-to-build-a-shed-ramp/)
- [How to Install a Gravel Pad Under a Shed](/guides/how-to-install-a-gravel-pad-under-a-shed/)
- [How to Lay a Concrete Garden Path](/guides/how-to-lay-a-concrete-garden-path/)
- [How to Lay a Greenhouse Base](/guides/how-to-lay-a-greenhouse-base/)

## FAQ

**How thick should a shed pad be?**
About four inches for a garden shed, thicker for anything heavy.

**Do I need rebar in a shed pad?**
Mesh helps on soft ground or a large pad. A small shed pad usually copes without.

**How long before I can build on it?**
A week for foot traffic, longer before a heavy shed goes on.

**Can I build a shed on gravel instead?**
Yes for a light shed, if the base is compacted and edged. Concrete lasts longer.

When to call a pro: The shed is large, the ground slopes more than a few inches, or the pad has to carry a heavy load.
Safety: Call before you dig, since shed sites often sit over service lines. Wear boots and gloves, and keep wet concrete off your skin, because cement burns. Lift bags and wheelbarrow loads with your legs.

General information only, not professional advice. Rules vary by state and city. First Home Fixes, https://firsthomefixes.com