First Home Fixes logo

Home / Garage and Outdoors

How to Set Fence Posts in Concrete

5 min read · Updated 28 November 2026 ·

Part of: Outdoors and garage

Simple diagram for the guide: How to Set Fence Posts in Concrete
Difficulty
Moderate
Time
A weekend
Tools
Post hole digger, spade, tape measure, string line, level, wheelbarrow, bucket, gravel, concrete mix, water, braces, gloves, safety glasses
Call a pro if
You hit a utility line or solid rock, the ground is on a steep slope, or the fence is tall or on a property line with rules, since those need a locator, a pro or a permit.
In this guide
  1. Call 811 before you dig
  2. Lay out the fence line
  3. Work out the post depth
  4. Dig the holes
  5. Set the first post
  6. Mix and pour the concrete
  7. Repeat with the string as your guide
  8. Cure before you build
  9. Attach the fence and finish
  10. Common mistakes
  11. FAQ
  12. When to call a pro
Safety. Call 811 before you dig, every time, since a post hole is deep enough to hit a gas, water or power line. Keep the concrete mix out of your eyes and off your skin, wear gloves and eye protection, and do not lift a full bag of mix on your own if it is too heavy.

A fence is only as good as its posts. The rails and pickets can be replaced in an afternoon, but a post that leans or rots at the base means digging out concrete. Setting posts properly is slow, physical work with a few rules that decide whether the fence is straight in five years. How to set fence posts in concrete starts with a call to 811, at least a few days before you dig.

1. Call 811 before you dig

1. Contact the 811 service in your area at least a few days before you plan to dig.

2. Mark the proposed line with paint or stakes so the locator knows where to look.

3. Wait for the utilities to mark their lines and keep the flags in place.

4. Hand dig near any marked line, never with a machine.

5. If you hit something you cannot identify, stop and call the utility.

2. Lay out the fence line

1. Decide the line and check the property boundary before you dig.

2. Run a string line between the end points at the height of the top rail.

3. Mark each post position along the line, keeping the spacing even.

4. Keep panels to a length the rails will span, usually 6 or 8 feet.

5. Check local rules for height, setbacks and permits.

3. Work out the post depth

1. Set posts about a third of their length in the ground, and always below the frost line where the ground freezes.

2. A 6 foot fence usually means an 8 foot post with about 2 to 3 feet buried.

3. Make the hole about three times the width of the post.

4. Add a few inches of gravel at the bottom for drainage.

5. Keep the hole sides rough, since smooth sides let the concrete plug slide up with frost.

4. Dig the holes

1. Dig with a post hole digger, then clean the bottom with a spade.

2. Check the depth with a tape measure on the post, not on the digger.

3. Keep the holes clear of loose soil that will settle later.

4. Place the spoil pile away from the hole so it does not fall back in.

5. Dig all the holes before mixing any concrete, so the pour is one session.

5. Set the first post

1. Put the post in the hole and check it against the string line.

2. Plumb it on two faces with a level.

3. Brace it with two scrap boards screwed to stakes, so it cannot move.

4. Check the height against the string and adjust.

5. Recheck the level after bracing, since bracing can push a post out.

6. Mix and pour the concrete

1. Mix the concrete to the consistency on the bag, in a wheelbarrow.

2. Pour in stages and tamp it with a stick to remove air pockets.

3. Fill to a few inches below grade, then slope the top away from the post so water runs off.

4. Recheck plumb while the concrete is still wet.

5. Clean the post above the concrete with a wet rag before it sets.

7. Repeat with the string as your guide

1. Set the next post and check the line, the height and the plumb.

2. Keep the spacing consistent, since rails are cut to a standard length.

3. Work along the line rather than jumping around.

4. Check every post against the two end posts, not just the one before it.

5. Leave the braces on until the concrete has set.

8. Cure before you build

1. Keep people and pets away from the posts for at least 24 hours.

2. Do not hang rails or gates until the concrete has cured, usually a few days.

3. Keep the concrete damp for the first day in hot weather if the label says to.

4. Backfill around the concrete with soil and tamp it.

5. Remove the braces only when the posts feel solid.

9. Attach the fence and finish

1. Fix the rails at a consistent height using the string as a guide.

2. Hang the gate last, and check it swings clear and latches.

3. Cap the posts if you want to slow water damage at the top.

4. Check the whole line for lean after the first rain.

5. Treat or seal cut ends on wood posts.

Our guide on fixing a leaning fence post covers a post that has already moved.

Common mistakes

FAQ

How deep should a fence post be set?

About a third of the post length, and below the frost line. A 6 foot fence usually needs 2 to 3 feet in the ground.

Should I use concrete or just gravel?

Concrete holds a post firm and resists frost heave better in most soils. Gravel drains well but allows movement.

How long does the concrete take to set?

It sets enough to hold the post in about a day and reaches working strength in a few days. Wait before hanging gates.

Can I set posts in frozen ground?

It is very difficult and the concrete will not cure properly. Wait for a thaw or use a different fence type.

how to set fence posts in concretefence post installationpost hole depthconcrete fence postdiy fence

Related guides

Simple diagram for the guide: How to Install a Mailbox Post That Stays UprightGarage and OutdoorsHow to Install a Mailbox Post That Stays UprightLearn how to install a mailbox post: check the placement rules, dig and set the post in concrete, mount the box at the right height and keep it solid.Simple illustration for the guide How to Mix a Small Batch of ConcreteGarage and OutdoorsHow to Mix a Small Batch of ConcreteLearn how to mix a small batch of concrete: measure by volume, add water gradually and work fast enough to place it before it sets.Simple illustration for the guide How to Use a CrowbarGarage and OutdoorsHow to Use a CrowbarLearn how to use a crowbar without wrecking the material: set the claw in a seam, pry in small lifts and protect the surface under it.Simple illustration for the guide How to Use a FileGarage and OutdoorsHow to Use a FileLearn how to use a file on metal, wood and plastic: pick the right cut, hold it flat, and file in one direction with steady pressure.Simple illustration for the guide How to Use a Plumb BobGarage and OutdoorsHow to Use a Plumb BobLearn how to use a plumb bob to find true vertical: hang it from a steady point, let it settle and mark the point below before you measure.